Concrete Deterioration
Hitech were engaged to remove concrete from the face of a ROM Backstop via means of Hydro Demolition, in order for the steel reinforcement to remain intact. Two trained operators removed approx 2m³ of concrete with a hand gun operated high pressure pump, within 2.5 shifts including site establishment.
The client was pleased with the results we achieved so quickly and was very impressed with the effectiveness of our machine.