Project Details
Concrete Cutting
As part of the Legacy Way Transcity Joint Venture, Hitech was engaged to carry out the hydro-demolition of a concrete ramp. The project included Robotic Hydro Demolition of 42 m3.
We utilised an Aqua Spine and our Aquacutter 710v Robot. All work was carried out on night shift due to other work groups in the area. Hitech achieved 43m3 of concrete removal in 18 nights shifts of work. As a final process, we then mobilised our handgun pump to the site to carry out the removal of any shadows that may have been missed by the robots.